The UK has 586 listed data centres, the second most of any country after the US (5,037) src. In 2024 data centres in Great Britain used about 4.5 TWh of grid electricity, roughly 2% of the total, up 41% since 2020 src.
Existing hubs AI Growth Zones Major new projects
77% of GB data centre electricity is consumed in London and the South East src, led by Slough (29% on its own).
NESO forecasts data centre demand reaching about 5.2 GW and just over 20 TWh by 2030 src, more than four times 2024. Meanwhile 50.8 GW of data centre projects are seeking a transmission connection src.
Since September 2024, UK data centres have been designated Critical National Infrastructure src.